Crusoe
Denver AI data-center developer, valued at about $30.9B, that sold its southeast Wyoming campus site to Google in November 2026.
Crusoe develops and operates data centers for AI workloads. TechCrunch puts its recent valuation at about $30.9B after a $3.9B raise in September 2026.
Wyoming site sale
On Nov 6 2026 Crusoe said Google had acquired its data-center site in southeast Wyoming, a project it had announced in 2025 with Blackstone-backed Tallgrass Energy and planned to scale to 10 GW. Crusoe says the sale completes its pre-development work (site selection, approvals and a hybrid power plan of fuel cells, grid power and gas turbines, with carbon capture through Tallgrass’s sequestration hub). The price was not disclosed. Google had announced a $17B investment in the campus the day before. Bloomberg reported in June that Google had raised cost and timeline concerns and that Crusoe had been pushed aside; that is reporting, not confirmed by either company. CEO Chase Lochmiller says Crusoe has more than 6 GW contracted (company claim). Crusoe is also developing Google’s campus in Armstrong County, Texas, near Amarillo.
Timeline
Every dated event in the wiki that involves Crusoe, newest first.
Crusoe confirmed the sale of its southeast Wyoming campus site, planned with Tallgrass Energy, a day after Google pledged $17B there; terms undisclosed. Bloomberg had reported Google raised cost and timeline concerns (reported).
Connections
Crusoe and everything one link away. Drag to move, scroll to zoom, click a node to open it.Open in the full graph →
What links here
Company Google
Cited by
Cited as a source by 1 timeline events.
1 articles cite Crusoe as a source: Google